When should a Form 1501 be submitted?

  1. Within 10 calendar days after completing any installation

  2. Within 10 days of initiating construction

  3. Within 30 days after installation completion

  4. Within one year of installation

The correct answer is: Within 10 calendar days after completing any installation

Submitting a Form 1501 within 10 calendar days after completing any installation is crucial because this form is used to notify the appropriate regulatory agency about the completion of the installation of a compressed natural gas (CNG) system. Timely submission ensures that the installation can be reviewed and assessed for compliance with safety and operational standards. Staying within this specific time frame enhances accountability and allows for proper regulation of CNG facilities, ultimately contributing to the safety of both operators and the public. Other options suggest different time frames, which may not align with regulatory requirements. For instance, waiting longer than 10 days could lead to oversight or delays in necessary inspections and approvals. The intent behind the 10-calendar-day requirement is to encourage prompt communication following the completion of installations, thereby facilitating efficient oversight and operations in the CNG sector.